It was also planned to pump the water from the lake to the well. However, this ambitious project of the city flopped.

Initially, an oxidation pond was constructed for the landfill side 10 years ago near Sadarpur village in Palanpur by the Gujarat Urban Development Corporation of the Government of Gujarat. The kind of waste that was supposed to be dumped here by grading did not come, so the whole project has collapsed.

As the project has been unfinished for years, the plastic material like water pure fire cover brought from Netherlands at a cost of more than 5 crores has been cut and stolen by some unknown people.

Flopped of this ambitious project of the city

Further, under this entire project, apart from Palanpur, the graded waste from surrounding municipalities including Disa, Tharad and Dhanera was to come here, which was to be smothered with a two to three feet layer of indestructible plastic and thus fill the entire lake.

When it rains in monsoon, a system was arranged to collect water in the lower side. It was also planned to pump the water from the lake to the well. However, this ambitious project of the city flopped.

The plastic brought from the Netherlands was taken away by people from all around

In the end, plastic brought from the Netherlands has been taken by people from all over. It was a kind of material that was not found anywhere in India. Jio memran was also covered under the plastic. If all this has to be relaid, the whole project can be restarted. We saved this for three years earlier, but now there is nothing.”